A system has n resources R 0 ,..., R n-1 , and k processes P 0 ,.....P k-1 . The implementation of the resource request logic of each process P i . is as follows: if (i% 2==0) { if (i<n) request R i ; if (i+2<n)request R i+2 ; } else { if (i<n) request R n-i ; if (i+2<n)request R n-i-2 ; } In which one of the following situations is a deadlock possible?

(A) n = 40,k = 26

(B) n = 21,k = 12

(C) n = 20,k = 10

(D) n = 41,k = 19